Offline preview. Layer 2 only — the deterministic pricing engine. No model call, no network, no API key. The scope, the wage table and the comparable awards are all fixtures, so nothing on this page is valid for bidding; the point is to see the report and its charts render. For the real pipeline, use the estimator.
Tidiverse Studio · we estimate better

Preliminary Bid Proposal

Conceptual estimate · AACE Class 4–5 · ±20–30%

Quotation
Q-00000000
Issued
January 15, 2026
Valid until
February 14, 2026
Revision
0
Prepared for

U.S. Army Corps of Engineers, Los Angeles District

Prepared by

WestphalianFresco Construction

1400 Harbor Blvd, Long Beach CA · (562) 555-0142 · CAGE 8X4T2

Project

Renovation of Building 214, Vehicle Maintenance Facility

Los Angeles County, CA · NAICS 236220 · PSC Z2AA · 18,500 SF

01

Quoted price

Recommended bid price
$1,244,359

$67 / SF · $155,545 / month × 8

Below the local p25Bond included
Acceptable range
Aggressive$1,151,032−$93,327
Recommended$1,244,359—
Conservative$1,368,795+$124,436

$217,763 between floor and ceiling. The cost is identical in all three — only fee and contingency move.

02

Bid band and market position

The recommended price is below the lower quartile of comparable awards — either a real cost advantage or missing scope. Confirm which before submitting.

Bid band against the local median award

One estimate, three commercial postures. The cost is identical in all three — only fee and contingency move.

  • Local median
$0$1.0M$2.0MLocal median $1.9MAggressivePriced to win$1,151,032−41.0% vs medianRecommendedThe balanced position$1,244,359−36.2% vs medianConservativePriced to absorb surprises$1,368,795−29.8% vs median

Fee is the contractor's profit. Contingency is the allowance carried for what the solicitation did not say. Lowering either lowers the bid and raises the risk the contractor absorbs after award.

Table view
PostureFeeContingencyBid pricevs local median
Aggressive4.00%5.00%$1,151,032−41.0%
Recommended8.00%10.00%$1,244,359−36.2%
Conservative12.00%18.00%$1,368,795−29.8%

Where this bid sits in the local market

The bid band against 16 comparable federal awards in Los Angeles County, CA.

  • This bid band
  • Comparable awards, p25–p75
$1.0M$2.0M$3.0MLocal median $1.9MComparable local awardsThis bid bandAggressive $1.2M — Conservative $1.4M$1,244,359

Each tick on the lower lane is one awarded contract. The vertical rule is the local median. Award amounts include the winning contractor's own fee and risk premium, and are not costs.

Table view
Reference pointAmount
Aggressive bid$1,151,032
Recommended bid$1,244,359
Conservative bid$1,368,795
Local p25$1,681,250
Local median (p50)$1,950,000
Local p75$2,300,000
Aggressive
$1,151,032
fee 4.0% · cont 5.0% · −41% vs median

Half the usual fee and half the usual contingency — a bid to keep crews working. Every unknown that surfaces after award comes out of margin.

Recommended
$1,244,359
fee 8.0% · cont 10.0% · −36% vs median

The contractor's own fee and contingency schedule, unchanged. Use this unless there is a reason to move.

Conservative
$1,368,795
fee 12.0% · cont 18.0% · −30% vs median

Fee up by half, contingency up by four-fifths. For loosely written scope, an unseen site, a compressed schedule, or inferred quantities.

Fixture comparables. A real run queries USAspending for federal contract awards in the same state and NAICS over the last three years.

03

Cost and price structure

What the price is made of, and where the underlying cost sits.

Composition of the quoted price

Four groups that sum exactly to the bid price.

Bid price$1,244,359
  • Direct cost$844,141
  • Overhead & G&A$177,270
  • Fee$81,713
  • Insurance, contingency & bond$141,235
Table view
ComponentAmountShare
Direct cost$844,14167.8%
Overhead & G&A$177,27014.2%
Fee$81,7136.6%
Insurance, contingency & bond$141,23511.3%
Bid price$1,244,359100.0%

Direct cost by CSI division

Labor, material, equipment and subcontract for each division, before any markup.

26 · Electrical$368,73543.7%07 · Thermal & Moisture Protection$205,30224.3%23 · Heating, Ventilating & Air Conditi…$86,98410.3%03 · Concrete$82,4999.8%04 · Masonry$48,0295.7%08 · Openings$31,2683.7%09 · Finishes$21,3252.5%
Table view
DivisionDirect costShare
26 · Electrical$368,73543.7%
07 · Thermal & Moisture Protection$205,30224.3%
23 · Heating, Ventilating & Air Conditioning$86,98410.3%
03 · Concrete$82,4999.8%
04 · Masonry$48,0295.7%
08 · Openings$31,2683.7%
09 · Finishes$21,3252.5%
Total direct cost$844,141100.0%

Direct cost by type

What the direct cost is spent on, before any markup.

Total direct cost$844,141
  • Labor$339,676
  • Material$504,465
Table view
ComponentAmountShare
Labor$339,67640.2%
Material$504,46559.8%
Total direct cost$844,141100.0%
Full markup waterfall
Direct cost (labor + material + equipment + subs)$844,141
Field overhead10.00%$84,414
Field cost$928,556
Home office overhead6.00%$55,713
G&A4.00%$37,142
Cost before fee$1,021,411
Fee8.00%$81,713
Insurance2.00%$20,428
Contingency10.00%$102,141
Cost before bond$1,225,693
Bond premium (grossed up)1.50%$18,665
Bid price$1,244,359
04

Schedule of work

Quantities as extracted, priced against the rate catalog. A line the engine could not match to a rate is shown unpriced rather than approximated.

DivWork itemQuantityHrsLaborMaterialDirect cost
03Slab on grade replacement12,000 SF420$28,499$54,000$82,499
04CMU partition walls3,200 SF384$27,229$20,800$48,029
07Roof tear-off and disposalqty inferred18,500 SF333$21,479$15,725$37,204
07Roof insulation boardqty inferred18,500 SF222$15,744$48,100$63,844
0760-mil TPO membraneqty inferred18,500 SF407$28,864$62,900$91,764
07Perimeter edge metalqty assumed560 LF56$4,650$7,840$12,490
26Lighting and branch wiring18,500 SF1665$165,235$203,500$368,735
23HVAC replacement, office areaqty assumed4,000 SF320$30,984$56,000$86,984
08Hollow metal doors32 EA48$4,068$27,200$31,268
09Interior repaint24,000 SF192$12,925$8,400$21,325
Total direct cost4047$844,141
05

Basis of estimate

Delivery method
Design Bid Build
Duration
8 months
Place of performance
Los Angeles County, CA
Davis-Bacon
Applies
Wage determination
FIXTURE-DO-NOT-USE-IN-PROD
Material pricing
Uncalibrated catalog defaults
Comparable awards
16 · median $1,950,000
Crew hours
4047
Assumption set
v0 · 0/94 calibrated
Manual adjustments
None
Source
fixture scope (offline preview)
Report ID
Q-00000000 · engine 1.0.0
Markup schedule
MarkupAppliedCatalog default
Labor burden35.00%35.00%
Field overhead10.00%10.00%
Home office overhead6.00%6.00%
G&A4.00%4.00%
Fee8.00%8.00%
Insurance2.00%2.00%
Contingency10.00%10.00%
Bond rate1.50%1.50%
06

Qualifications and open items

This proposal is offered subject to the following. Each is a limit on what the price covers, or a question whose answer could move it.

Qualifications and exclusions5
  1. Using fixture wage rates, not a real Davis-Bacon determination. Not valid for bidding.
  2. 10 line(s) use system default rates that have not been calibrated against your historical projects. These are placeholders.
  3. 2 quantity/quantities were inferred, not stated in the RFP: Perimeter edge metal, HVAC replacement, office area
  4. Cross-check: $1,244,359 is below the p25 of comparable awards ($1,681,250, n=16). Possible missing scope.
  5. 2 item(s) of required information are missing from the RFP.
Information missing from the solicitation2
  1. Existing slab thickness and reinforcement are not stated, so the demolition and disposal allowance is an assumption.
  2. No hazardous materials survey is attached; the roof tear-off is priced as non-hazardous.
Questions for the contracting officer2
  1. Is asbestos abatement required in the roofing assembly, and if so is it in this contract or a separate one?
  2. Will the facility remain occupied during construction, and are there restricted working hours?
07

Estimator's notes

The roof scope drives this estimate: tear-off, insulation, membrane and edge metal together account for the largest share of direct cost, and all four quantities were inferred from the building footprint rather than stated in the solicitation. If the actual roof area differs from the gross floor area, this figure moves with it. Labor is priced against a fixture wage table, not a real determination, so the labor half of every line is indicative only.
08

Acceptance

Offered at $1,244,359, valid until February 14, 2026, subject to the qualifications above and to a site visit. The commercial range runs $1,151,032 to $1,368,795; a price outside it is a different scope, not a different negotiation.

Accepted for the client
Signature · printed name · title · date
For the contractor
WestphalianFresco Construction · date
A conceptual estimate for budgeting and bid strategy, not a bid guarantee — expected accuracy ±20–30% (AACE Class 4–5). Verify quantities, unit prices and assumptions, and have key items reviewed by a registered estimator, before submitting. Every amount here was produced by the deterministic pricing engine; the narrative describes those numbers and does not alter them. Comparable awards come from USAspending and are awarded contract values, which include the winner's fee and risk premium — they are not costs.